Six steps. One Olerra.
We've reduced the chaos of a custom build to a six-step playbook. You always know what's next, who's responsible, and when it's happening.
- Step 01Week 1Discovery call
30 minutes. We learn about your property, goals, and timeline. We send back a free feasibility summary.
- Step 02Weeks 2–3Site + zoning check
We pull your zoning, run an HOA review, and visit the site to confirm access for the crane and trailer.
- Step 03Weeks 3–5Design + quote
Pick model and finishes. We deliver a binding quote, drawings, and contract.
- Step 04Weeks 5–14Permits + foundation
We file with the municipality and pour the foundation while your unit is built in the factory.
- Step 05Weeks 6–18Factory build
Your Olerra is framed, wrapped, fitted, and inspected in our Loveland facility.
- Step 06Weeks 18–20Set + finish
Crane delivery, two-week tie-in, final inspection, and walk-through.